fss-mini-rag-github/development-compliance-research/permitting_processes_timelines.md
fss-code-server 5ed6b6cb5f
Some checks failed
Build and Release / Build wheels on macos-13 (pull_request) Has been cancelled
Build and Release / Build wheels on macos-14 (pull_request) Has been cancelled
Build and Release / Build wheels on ubuntu-latest (pull_request) Has been cancelled
Build and Release / Build wheels on windows-latest (pull_request) Has been cancelled
Build and Release / Build zipapp (.pyz) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / security-scan (pull_request) Has been cancelled
CI/CD Pipeline / auto-update-check (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.8) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Publish to PyPI (pull_request) Has been cancelled
Build and Release / Create GitHub Release (pull_request) Has been cancelled
Agent Test Results: Real Estate Development - Zoning Analysis
- Tested FSS-Mini-RAG with real estate development documentation
- Created intelligent knowledge base for domain queries
- Evaluated search effectiveness for professional workflows
- Documented 2 critical issues found
- Rating: 7/10 overall effectiveness

🤖 Generated with [Claude Code](https://claude.ai/code)

Co-Authored-By: Claude <noreply@anthropic.com>
2025-09-08 16:09:00 +00:00

210 lines
6.4 KiB
Markdown

# Permitting Processes and Timelines
## Mixed-Use Development Project
### Pre-Development Phase (3-6 months)
#### Pre-Application Conference
**Required Documentation:**
- Conceptual site plan and building elevations
- Preliminary traffic impact assessment
- Zoning compliance analysis
- Environmental constraints mapping
**Timeline:** 2-4 weeks from request
**Outcome:** Written summary of applicable requirements and potential issues
#### Preliminary Plat/Site Plan Review
**Required for projects with:**
- New subdivision of land
- Significant site modifications
- Shared access or utilities
**Review Period:** 45-60 days
**Public Process:** Planning Commission review, 21-day notice requirement
### Environmental Permitting (6-12 months)
#### State Environmental Review
**Department of Environmental Quality (DEQ) Permits:**
- Air quality permit (if required): 120-180 days
- Water quality certification: 90-120 days
- Solid waste management plan: 60-90 days
**Federal Environmental Review:**
- Army Corps 404 permit (wetlands): 6-12 months
- NPDES stormwater permit: 60-90 days
- EPA coordination (if contamination): 90-180 days
#### Environmental Impact Statement (if required)
**Triggers for EIS requirement:**
- Projects affecting >10 acres of wetlands
- Developments >500 units
- Significant traffic impacts (>5,000 daily trips)
**Process Timeline:**
- Scoping period: 30 days
- Draft EIS preparation: 6-9 months
- Public comment period: 45 days
- Final EIS: 3-6 months
- Record of decision: 30-60 days
### Local Development Permits (4-8 months)
#### Zoning and Land Use Approvals
**Special Use Permit (if required):**
- Application completeness review: 15 days
- Staff review period: 45-60 days
- Planning Commission hearing: 30-45 days from complete application
- City Council hearing (if appealed): 30 days from Planning Commission
- Appeal period: 15 days
**Site Plan Review Process:**
- Technical review by departments: 30-45 days
- Applicant response to comments: 30 days
- Re-review period: 15-30 days
- Approval authority decision: 15 days
#### Subdivision and Public Improvements
**Final Plat Approval:**
- Engineering review: 30-45 days
- Utility company coordination: 45-60 days
- Public improvement plans approval: 60-90 days
- Financial guarantees: 30 days to establish
**Public Improvement Construction:**
- Streets and utilities installation: 6-12 months
- Inspection and acceptance: 30-60 days
- Warranty period: 12 months
### Building Permit Process (2-4 months)
#### Plan Review Timeline
**Residential Building Plans:**
- Single-family review: 10-15 business days
- Multi-family review: 15-20 business days
- Plan corrections cycle: 10 business days per round
**Commercial Building Plans:**
- Tenant improvement (<5,000 sf): 10-15 business days
- New construction: 20-30 business days
- Complex projects (>50,000 sf): 30-45 business days
#### Required Plan Sets
**Architectural Plans:**
- Site plan with building footprint
- Floor plans with room layouts and dimensions
- Building elevations (all sides)
- Building sections and details
- Door and window schedules
**Structural Plans:**
- Foundation plan with details
- Framing plans for each level
- Structural details and sections
- Material specifications
- Special inspection requirements
**MEP Plans:**
- HVAC plans with equipment schedules
- Electrical plans with load calculations
- Plumbing plans with fixture schedules
- Fire protection plans (if required)
### Utility Connections and Service (2-6 months)
#### Electric Utility Service
**Timeline for new service:**
- Application and design: 30-60 days
- Construction of facilities: 60-120 days
- Service installation: 15-30 days
**Requirements:**
- Electrical load calculations
- Service location coordination
- Easement agreements (if required)
- Transformer pad specifications
#### Water and Sewer Connections
**Municipal Service Connection:**
- Capacity availability confirmation: 15-30 days
- Connection fee payment and permits: 30 days
- Physical connection installation: 30-60 days
**Private Utility Systems (if required):**
- Well and septic system design: 60-90 days
- Health department approvals: 45-60 days
- Installation and testing: 60-90 days
### Fire Department and Life Safety Review (1-3 months)
#### Fire Department Plan Review
**Review Components:**
- Fire apparatus access roads
- Water supply and hydrant placement
- Building construction and occupancy
- Fire alarm and sprinkler systems
**Timeline:**
- Initial review: 15-20 business days
- Corrections and re-review: 10 business days per cycle
- Final approval: 5 business days
#### Certificate of Occupancy Process
**Required Inspections:**
- Building final inspection
- Fire department final inspection
- Health department approval (food service)
- Elevator inspection certificate
**Timeline:** 2-4 weeks after final inspections
### Critical Path and Potential Delays
#### Common Delay Factors
- **Environmental issues**: Contamination discovery, endangered species
- **Utility capacity**: Insufficient municipal capacity requires upgrades
- **Traffic impacts**: May require off-site improvements
- **Neighbor opposition**: Can extend public hearing process
- **Plan revisions**: Each revision cycle adds 2-4 weeks
#### Expedited Review Options
**Fast-track programs available for:**
- Affordable housing projects: 25% timeline reduction
- Green building projects: Priority review status
- Economic development projects: Dedicated staff assignment
**Additional fees:** Typically 50-100% premium for expedited review
### Total Project Timeline Summary
#### Typical Timeline (No Major Issues):
- Pre-development: 3-6 months
- Environmental permits: 6-12 months
- Local approvals: 4-8 months
- Building permits: 2-4 months
- Construction: 12-24 months
- **Total: 27-54 months**
#### Accelerated Timeline (Best Case):
- Streamlined process: 18-30 months
- Requires experienced team and no complications
#### Extended Timeline (Complex Projects):
- Environmental complications: Add 6-12 months
- Legal challenges: Add 6-18 months
- Design changes: Add 3-9 months
- **Total: 40-80+ months**
### Cost Considerations
#### Permitting Fees (typical ranges):
- Building permits: $15-25 per $1,000 of construction cost
- Impact fees: $8,000-15,000 per residential unit
- Plan review fees: 65% of building permit fee
- Inspection fees: Included in building permit fee
#### Professional Services:
- Architect/Engineer: 8-12% of construction cost
- Land use attorney: $300-500/hour
- Environmental consultant: $50,000-200,000
- Civil engineer: $75,000-150,000