fss-mini-rag-github/development-compliance-research/permitting_processes_timelines.md
fss-code-server 5ed6b6cb5f
Some checks failed
Build and Release / Build wheels on macos-13 (pull_request) Has been cancelled
Build and Release / Build wheels on macos-14 (pull_request) Has been cancelled
Build and Release / Build wheels on ubuntu-latest (pull_request) Has been cancelled
Build and Release / Build wheels on windows-latest (pull_request) Has been cancelled
Build and Release / Build zipapp (.pyz) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / security-scan (pull_request) Has been cancelled
CI/CD Pipeline / auto-update-check (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.8) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Publish to PyPI (pull_request) Has been cancelled
Build and Release / Create GitHub Release (pull_request) Has been cancelled
Agent Test Results: Real Estate Development - Zoning Analysis
- Tested FSS-Mini-RAG with real estate development documentation
- Created intelligent knowledge base for domain queries
- Evaluated search effectiveness for professional workflows
- Documented 2 critical issues found
- Rating: 7/10 overall effectiveness

🤖 Generated with [Claude Code](https://claude.ai/code)

Co-Authored-By: Claude <noreply@anthropic.com>
2025-09-08 16:09:00 +00:00

6.4 KiB

Permitting Processes and Timelines

Mixed-Use Development Project

Pre-Development Phase (3-6 months)

Pre-Application Conference

Required Documentation:

  • Conceptual site plan and building elevations
  • Preliminary traffic impact assessment
  • Zoning compliance analysis
  • Environmental constraints mapping

Timeline: 2-4 weeks from request Outcome: Written summary of applicable requirements and potential issues

Preliminary Plat/Site Plan Review

Required for projects with:

  • New subdivision of land
  • Significant site modifications
  • Shared access or utilities

Review Period: 45-60 days Public Process: Planning Commission review, 21-day notice requirement

Environmental Permitting (6-12 months)

State Environmental Review

Department of Environmental Quality (DEQ) Permits:

  • Air quality permit (if required): 120-180 days
  • Water quality certification: 90-120 days
  • Solid waste management plan: 60-90 days

Federal Environmental Review:

  • Army Corps 404 permit (wetlands): 6-12 months
  • NPDES stormwater permit: 60-90 days
  • EPA coordination (if contamination): 90-180 days

Environmental Impact Statement (if required)

Triggers for EIS requirement:

  • Projects affecting >10 acres of wetlands
  • Developments >500 units
  • Significant traffic impacts (>5,000 daily trips)

Process Timeline:

  • Scoping period: 30 days
  • Draft EIS preparation: 6-9 months
  • Public comment period: 45 days
  • Final EIS: 3-6 months
  • Record of decision: 30-60 days

Local Development Permits (4-8 months)

Zoning and Land Use Approvals

Special Use Permit (if required):

  • Application completeness review: 15 days
  • Staff review period: 45-60 days
  • Planning Commission hearing: 30-45 days from complete application
  • City Council hearing (if appealed): 30 days from Planning Commission
  • Appeal period: 15 days

Site Plan Review Process:

  • Technical review by departments: 30-45 days
  • Applicant response to comments: 30 days
  • Re-review period: 15-30 days
  • Approval authority decision: 15 days

Subdivision and Public Improvements

Final Plat Approval:

  • Engineering review: 30-45 days
  • Utility company coordination: 45-60 days
  • Public improvement plans approval: 60-90 days
  • Financial guarantees: 30 days to establish

Public Improvement Construction:

  • Streets and utilities installation: 6-12 months
  • Inspection and acceptance: 30-60 days
  • Warranty period: 12 months

Building Permit Process (2-4 months)

Plan Review Timeline

Residential Building Plans:

  • Single-family review: 10-15 business days
  • Multi-family review: 15-20 business days
  • Plan corrections cycle: 10 business days per round

Commercial Building Plans:

  • Tenant improvement (<5,000 sf): 10-15 business days
  • New construction: 20-30 business days
  • Complex projects (>50,000 sf): 30-45 business days

Required Plan Sets

Architectural Plans:

  • Site plan with building footprint
  • Floor plans with room layouts and dimensions
  • Building elevations (all sides)
  • Building sections and details
  • Door and window schedules

Structural Plans:

  • Foundation plan with details
  • Framing plans for each level
  • Structural details and sections
  • Material specifications
  • Special inspection requirements

MEP Plans:

  • HVAC plans with equipment schedules
  • Electrical plans with load calculations
  • Plumbing plans with fixture schedules
  • Fire protection plans (if required)

Utility Connections and Service (2-6 months)

Electric Utility Service

Timeline for new service:

  • Application and design: 30-60 days
  • Construction of facilities: 60-120 days
  • Service installation: 15-30 days

Requirements:

  • Electrical load calculations
  • Service location coordination
  • Easement agreements (if required)
  • Transformer pad specifications

Water and Sewer Connections

Municipal Service Connection:

  • Capacity availability confirmation: 15-30 days
  • Connection fee payment and permits: 30 days
  • Physical connection installation: 30-60 days

Private Utility Systems (if required):

  • Well and septic system design: 60-90 days
  • Health department approvals: 45-60 days
  • Installation and testing: 60-90 days

Fire Department and Life Safety Review (1-3 months)

Fire Department Plan Review

Review Components:

  • Fire apparatus access roads
  • Water supply and hydrant placement
  • Building construction and occupancy
  • Fire alarm and sprinkler systems

Timeline:

  • Initial review: 15-20 business days
  • Corrections and re-review: 10 business days per cycle
  • Final approval: 5 business days

Certificate of Occupancy Process

Required Inspections:

  • Building final inspection
  • Fire department final inspection
  • Health department approval (food service)
  • Elevator inspection certificate

Timeline: 2-4 weeks after final inspections

Critical Path and Potential Delays

Common Delay Factors

  • Environmental issues: Contamination discovery, endangered species
  • Utility capacity: Insufficient municipal capacity requires upgrades
  • Traffic impacts: May require off-site improvements
  • Neighbor opposition: Can extend public hearing process
  • Plan revisions: Each revision cycle adds 2-4 weeks

Expedited Review Options

Fast-track programs available for:

  • Affordable housing projects: 25% timeline reduction
  • Green building projects: Priority review status
  • Economic development projects: Dedicated staff assignment

Additional fees: Typically 50-100% premium for expedited review

Total Project Timeline Summary

Typical Timeline (No Major Issues):

  • Pre-development: 3-6 months
  • Environmental permits: 6-12 months
  • Local approvals: 4-8 months
  • Building permits: 2-4 months
  • Construction: 12-24 months
  • Total: 27-54 months

Accelerated Timeline (Best Case):

  • Streamlined process: 18-30 months
  • Requires experienced team and no complications

Extended Timeline (Complex Projects):

  • Environmental complications: Add 6-12 months
  • Legal challenges: Add 6-18 months
  • Design changes: Add 3-9 months
  • Total: 40-80+ months

Cost Considerations

Permitting Fees (typical ranges):

  • Building permits: $15-25 per $1,000 of construction cost
  • Impact fees: $8,000-15,000 per residential unit
  • Plan review fees: 65% of building permit fee
  • Inspection fees: Included in building permit fee

Professional Services:

  • Architect/Engineer: 8-12% of construction cost
  • Land use attorney: $300-500/hour
  • Environmental consultant: $50,000-200,000
  • Civil engineer: $75,000-150,000