# Permitting Processes and Timelines ## Mixed-Use Development Project ### Pre-Development Phase (3-6 months) #### Pre-Application Conference **Required Documentation:** - Conceptual site plan and building elevations - Preliminary traffic impact assessment - Zoning compliance analysis - Environmental constraints mapping **Timeline:** 2-4 weeks from request **Outcome:** Written summary of applicable requirements and potential issues #### Preliminary Plat/Site Plan Review **Required for projects with:** - New subdivision of land - Significant site modifications - Shared access or utilities **Review Period:** 45-60 days **Public Process:** Planning Commission review, 21-day notice requirement ### Environmental Permitting (6-12 months) #### State Environmental Review **Department of Environmental Quality (DEQ) Permits:** - Air quality permit (if required): 120-180 days - Water quality certification: 90-120 days - Solid waste management plan: 60-90 days **Federal Environmental Review:** - Army Corps 404 permit (wetlands): 6-12 months - NPDES stormwater permit: 60-90 days - EPA coordination (if contamination): 90-180 days #### Environmental Impact Statement (if required) **Triggers for EIS requirement:** - Projects affecting >10 acres of wetlands - Developments >500 units - Significant traffic impacts (>5,000 daily trips) **Process Timeline:** - Scoping period: 30 days - Draft EIS preparation: 6-9 months - Public comment period: 45 days - Final EIS: 3-6 months - Record of decision: 30-60 days ### Local Development Permits (4-8 months) #### Zoning and Land Use Approvals **Special Use Permit (if required):** - Application completeness review: 15 days - Staff review period: 45-60 days - Planning Commission hearing: 30-45 days from complete application - City Council hearing (if appealed): 30 days from Planning Commission - Appeal period: 15 days **Site Plan Review Process:** - Technical review by departments: 30-45 days - Applicant response to comments: 30 days - Re-review period: 15-30 days - Approval authority decision: 15 days #### Subdivision and Public Improvements **Final Plat Approval:** - Engineering review: 30-45 days - Utility company coordination: 45-60 days - Public improvement plans approval: 60-90 days - Financial guarantees: 30 days to establish **Public Improvement Construction:** - Streets and utilities installation: 6-12 months - Inspection and acceptance: 30-60 days - Warranty period: 12 months ### Building Permit Process (2-4 months) #### Plan Review Timeline **Residential Building Plans:** - Single-family review: 10-15 business days - Multi-family review: 15-20 business days - Plan corrections cycle: 10 business days per round **Commercial Building Plans:** - Tenant improvement (<5,000 sf): 10-15 business days - New construction: 20-30 business days - Complex projects (>50,000 sf): 30-45 business days #### Required Plan Sets **Architectural Plans:** - Site plan with building footprint - Floor plans with room layouts and dimensions - Building elevations (all sides) - Building sections and details - Door and window schedules **Structural Plans:** - Foundation plan with details - Framing plans for each level - Structural details and sections - Material specifications - Special inspection requirements **MEP Plans:** - HVAC plans with equipment schedules - Electrical plans with load calculations - Plumbing plans with fixture schedules - Fire protection plans (if required) ### Utility Connections and Service (2-6 months) #### Electric Utility Service **Timeline for new service:** - Application and design: 30-60 days - Construction of facilities: 60-120 days - Service installation: 15-30 days **Requirements:** - Electrical load calculations - Service location coordination - Easement agreements (if required) - Transformer pad specifications #### Water and Sewer Connections **Municipal Service Connection:** - Capacity availability confirmation: 15-30 days - Connection fee payment and permits: 30 days - Physical connection installation: 30-60 days **Private Utility Systems (if required):** - Well and septic system design: 60-90 days - Health department approvals: 45-60 days - Installation and testing: 60-90 days ### Fire Department and Life Safety Review (1-3 months) #### Fire Department Plan Review **Review Components:** - Fire apparatus access roads - Water supply and hydrant placement - Building construction and occupancy - Fire alarm and sprinkler systems **Timeline:** - Initial review: 15-20 business days - Corrections and re-review: 10 business days per cycle - Final approval: 5 business days #### Certificate of Occupancy Process **Required Inspections:** - Building final inspection - Fire department final inspection - Health department approval (food service) - Elevator inspection certificate **Timeline:** 2-4 weeks after final inspections ### Critical Path and Potential Delays #### Common Delay Factors - **Environmental issues**: Contamination discovery, endangered species - **Utility capacity**: Insufficient municipal capacity requires upgrades - **Traffic impacts**: May require off-site improvements - **Neighbor opposition**: Can extend public hearing process - **Plan revisions**: Each revision cycle adds 2-4 weeks #### Expedited Review Options **Fast-track programs available for:** - Affordable housing projects: 25% timeline reduction - Green building projects: Priority review status - Economic development projects: Dedicated staff assignment **Additional fees:** Typically 50-100% premium for expedited review ### Total Project Timeline Summary #### Typical Timeline (No Major Issues): - Pre-development: 3-6 months - Environmental permits: 6-12 months - Local approvals: 4-8 months - Building permits: 2-4 months - Construction: 12-24 months - **Total: 27-54 months** #### Accelerated Timeline (Best Case): - Streamlined process: 18-30 months - Requires experienced team and no complications #### Extended Timeline (Complex Projects): - Environmental complications: Add 6-12 months - Legal challenges: Add 6-18 months - Design changes: Add 3-9 months - **Total: 40-80+ months** ### Cost Considerations #### Permitting Fees (typical ranges): - Building permits: $15-25 per $1,000 of construction cost - Impact fees: $8,000-15,000 per residential unit - Plan review fees: 65% of building permit fee - Inspection fees: Included in building permit fee #### Professional Services: - Architect/Engineer: 8-12% of construction cost - Land use attorney: $300-500/hour - Environmental consultant: $50,000-200,000 - Civil engineer: $75,000-150,000