Some checks failed
Build and Release / Build wheels on macos-13 (pull_request) Has been cancelled
Build and Release / Build wheels on macos-14 (pull_request) Has been cancelled
Build and Release / Build wheels on ubuntu-latest (pull_request) Has been cancelled
Build and Release / Build wheels on windows-latest (pull_request) Has been cancelled
Build and Release / Build zipapp (.pyz) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / security-scan (pull_request) Has been cancelled
CI/CD Pipeline / auto-update-check (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.8) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Publish to PyPI (pull_request) Has been cancelled
Build and Release / Create GitHub Release (pull_request) Has been cancelled
- Tested FSS-Mini-RAG with real estate development documentation - Created intelligent knowledge base for domain queries - Evaluated search effectiveness for professional workflows - Documented 2 critical issues found - Rating: 7/10 overall effectiveness 🤖 Generated with [Claude Code](https://claude.ai/code) Co-Authored-By: Claude <noreply@anthropic.com>
130 lines
4.6 KiB
Markdown
130 lines
4.6 KiB
Markdown
# Environmental Impact Assessment Requirements
|
|
## Mixed-Use Development Projects
|
|
|
|
### Phase I Environmental Site Assessment
|
|
**Required for all projects exceeding:**
|
|
- 2 acres of development
|
|
- 50 residential units
|
|
- 25,000 sq ft of commercial space
|
|
|
|
**Assessment Components:**
|
|
- Historical land use review dating back 50 years
|
|
- Review of environmental databases (CERCLIS, RCRA, UST)
|
|
- Site reconnaissance and photographic documentation
|
|
- Interviews with knowledgeable parties
|
|
- Assessment of recognized environmental conditions (RECs)
|
|
|
|
### Phase II Environmental Assessment Triggers
|
|
Required when Phase I identifies:
|
|
- Former gas stations or automotive facilities within 500 feet
|
|
- Dry cleaning operations (historical or current)
|
|
- Industrial facilities with chemical storage
|
|
- Underground storage tanks (active or abandoned)
|
|
- Soil or groundwater contamination potential
|
|
|
|
### Wetland Delineation Requirements
|
|
**Mandatory assessment if site contains:**
|
|
- Seasonal water accumulation areas
|
|
- Hydric soils indicators
|
|
- Wetland vegetation communities
|
|
- Areas within 100 feet of water bodies
|
|
|
|
**Process Requirements:**
|
|
- Professional wetland scientist evaluation
|
|
- Army Corps of Engineers jurisdictional determination
|
|
- 404 permit application if impacts exceed 0.1 acres
|
|
- Mitigation banking or on-site compensation plans
|
|
|
|
### Stormwater Management Compliance
|
|
**Post-Construction Requirements:**
|
|
- Retention of first 1.2 inches of rainfall on-site
|
|
- Peak discharge rates not to exceed pre-development conditions
|
|
- Water quality treatment for 90% of annual runoff
|
|
- Long-term maintenance agreements with approved entities
|
|
|
|
**Green Infrastructure Requirements:**
|
|
- Minimum 30% of stormwater managed through green infrastructure
|
|
- Permeable pavement for minimum 25% of parking areas
|
|
- Bioretention areas sized for 10-year storm events
|
|
- Tree canopy coverage of 40% within 10 years
|
|
|
|
### Air Quality Impact Analysis
|
|
**Required for projects with:**
|
|
- More than 500 vehicle trips per day
|
|
- Parking for 200+ vehicles
|
|
- Commercial uses generating odors or emissions
|
|
|
|
**Assessment Components:**
|
|
- Mobile source emission calculations
|
|
- Construction dust control plans
|
|
- Indoor air quality considerations for residential units
|
|
- Compliance with National Ambient Air Quality Standards
|
|
|
|
### Noise Impact Assessment
|
|
**Trigger Levels:**
|
|
- Projects within 1,500 feet of highways or arterial roads
|
|
- Mixed-use with late-night commercial operations
|
|
- Loading docks or mechanical equipment on-site
|
|
|
|
**Standards:**
|
|
- Residential areas: 55 dB daytime, 45 dB nighttime
|
|
- Commercial areas: 65 dB daytime, 55 dB nighttime
|
|
- Mitigation required if increases exceed 3 dB over ambient
|
|
|
|
### Historic and Cultural Resource Review
|
|
**Section 106 Review Required:**
|
|
- Properties 50+ years old within 0.5 miles
|
|
- Areas of known archaeological significance
|
|
- Traditional cultural properties consultation with tribal authorities
|
|
|
|
**Documentation Requirements:**
|
|
- Historic structures report
|
|
- Archaeological survey (if ground disturbance >1 acre)
|
|
- Tribal consultation documentation
|
|
- State Historic Preservation Office coordination
|
|
|
|
### Soil and Groundwater Assessment
|
|
**Contamination Screening:**
|
|
- Lead paint analysis for structures built before 1978
|
|
- Asbestos survey for buildings constructed 1940-1980
|
|
- Petroleum hydrocarbon testing near former fuel facilities
|
|
- Heavy metals analysis in urban brownfield areas
|
|
|
|
**Remediation Thresholds:**
|
|
- Residential soil standards apply to all residential components
|
|
- Groundwater monitoring required if contamination detected
|
|
- Vapor intrusion assessment for volatile compounds
|
|
- Institutional controls may be required for contained contamination
|
|
|
|
### Wildlife and Habitat Protection
|
|
**Protected Species Assessment:**
|
|
- Endangered species habitat surveys during breeding seasons
|
|
- Migratory bird nesting surveys (March-August)
|
|
- Tree surveys for protected or heritage specimens
|
|
- Pollinator habitat preservation requirements
|
|
|
|
### Construction Environmental Controls
|
|
**Erosion and Sediment Control:**
|
|
- SWPPP (Stormwater Pollution Prevention Plan) required
|
|
- Daily inspection and maintenance logs
|
|
- Stabilization within 7 days of final grade
|
|
- Temporary seeding for areas disturbed >30 days
|
|
|
|
**Dust Control Measures:**
|
|
- Water application during dry conditions
|
|
- Stabilized construction entrances
|
|
- Vehicle tracking prevention
|
|
- Air quality monitoring during demolition
|
|
|
|
### Timeline and Compliance
|
|
**Assessment Timeline:**
|
|
- Phase I ESA: 30-45 days
|
|
- Phase II ESA (if required): 60-90 days
|
|
- Wetland delineation: 45-60 days
|
|
- Species surveys: Season-dependent (3-6 months)
|
|
|
|
**Regulatory Approvals:**
|
|
- EPA coordination: 90-120 days
|
|
- Army Corps 404 permit: 6-12 months
|
|
- State environmental permits: 60-90 days
|
|
- Local environmental review: 30-60 days |