fss-mini-rag-github/development-compliance-research/environmental_impact_requirements.md
fss-code-server 5ed6b6cb5f
Some checks failed
Build and Release / Build wheels on macos-13 (pull_request) Has been cancelled
Build and Release / Build wheels on macos-14 (pull_request) Has been cancelled
Build and Release / Build wheels on ubuntu-latest (pull_request) Has been cancelled
Build and Release / Build wheels on windows-latest (pull_request) Has been cancelled
Build and Release / Build zipapp (.pyz) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / security-scan (pull_request) Has been cancelled
CI/CD Pipeline / auto-update-check (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.8) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Publish to PyPI (pull_request) Has been cancelled
Build and Release / Create GitHub Release (pull_request) Has been cancelled
Agent Test Results: Real Estate Development - Zoning Analysis
- Tested FSS-Mini-RAG with real estate development documentation
- Created intelligent knowledge base for domain queries
- Evaluated search effectiveness for professional workflows
- Documented 2 critical issues found
- Rating: 7/10 overall effectiveness

🤖 Generated with [Claude Code](https://claude.ai/code)

Co-Authored-By: Claude <noreply@anthropic.com>
2025-09-08 16:09:00 +00:00

4.6 KiB

Environmental Impact Assessment Requirements

Mixed-Use Development Projects

Phase I Environmental Site Assessment

Required for all projects exceeding:

  • 2 acres of development
  • 50 residential units
  • 25,000 sq ft of commercial space

Assessment Components:

  • Historical land use review dating back 50 years
  • Review of environmental databases (CERCLIS, RCRA, UST)
  • Site reconnaissance and photographic documentation
  • Interviews with knowledgeable parties
  • Assessment of recognized environmental conditions (RECs)

Phase II Environmental Assessment Triggers

Required when Phase I identifies:

  • Former gas stations or automotive facilities within 500 feet
  • Dry cleaning operations (historical or current)
  • Industrial facilities with chemical storage
  • Underground storage tanks (active or abandoned)
  • Soil or groundwater contamination potential

Wetland Delineation Requirements

Mandatory assessment if site contains:

  • Seasonal water accumulation areas
  • Hydric soils indicators
  • Wetland vegetation communities
  • Areas within 100 feet of water bodies

Process Requirements:

  • Professional wetland scientist evaluation
  • Army Corps of Engineers jurisdictional determination
  • 404 permit application if impacts exceed 0.1 acres
  • Mitigation banking or on-site compensation plans

Stormwater Management Compliance

Post-Construction Requirements:

  • Retention of first 1.2 inches of rainfall on-site
  • Peak discharge rates not to exceed pre-development conditions
  • Water quality treatment for 90% of annual runoff
  • Long-term maintenance agreements with approved entities

Green Infrastructure Requirements:

  • Minimum 30% of stormwater managed through green infrastructure
  • Permeable pavement for minimum 25% of parking areas
  • Bioretention areas sized for 10-year storm events
  • Tree canopy coverage of 40% within 10 years

Air Quality Impact Analysis

Required for projects with:

  • More than 500 vehicle trips per day
  • Parking for 200+ vehicles
  • Commercial uses generating odors or emissions

Assessment Components:

  • Mobile source emission calculations
  • Construction dust control plans
  • Indoor air quality considerations for residential units
  • Compliance with National Ambient Air Quality Standards

Noise Impact Assessment

Trigger Levels:

  • Projects within 1,500 feet of highways or arterial roads
  • Mixed-use with late-night commercial operations
  • Loading docks or mechanical equipment on-site

Standards:

  • Residential areas: 55 dB daytime, 45 dB nighttime
  • Commercial areas: 65 dB daytime, 55 dB nighttime
  • Mitigation required if increases exceed 3 dB over ambient

Historic and Cultural Resource Review

Section 106 Review Required:

  • Properties 50+ years old within 0.5 miles
  • Areas of known archaeological significance
  • Traditional cultural properties consultation with tribal authorities

Documentation Requirements:

  • Historic structures report
  • Archaeological survey (if ground disturbance >1 acre)
  • Tribal consultation documentation
  • State Historic Preservation Office coordination

Soil and Groundwater Assessment

Contamination Screening:

  • Lead paint analysis for structures built before 1978
  • Asbestos survey for buildings constructed 1940-1980
  • Petroleum hydrocarbon testing near former fuel facilities
  • Heavy metals analysis in urban brownfield areas

Remediation Thresholds:

  • Residential soil standards apply to all residential components
  • Groundwater monitoring required if contamination detected
  • Vapor intrusion assessment for volatile compounds
  • Institutional controls may be required for contained contamination

Wildlife and Habitat Protection

Protected Species Assessment:

  • Endangered species habitat surveys during breeding seasons
  • Migratory bird nesting surveys (March-August)
  • Tree surveys for protected or heritage specimens
  • Pollinator habitat preservation requirements

Construction Environmental Controls

Erosion and Sediment Control:

  • SWPPP (Stormwater Pollution Prevention Plan) required
  • Daily inspection and maintenance logs
  • Stabilization within 7 days of final grade
  • Temporary seeding for areas disturbed >30 days

Dust Control Measures:

  • Water application during dry conditions
  • Stabilized construction entrances
  • Vehicle tracking prevention
  • Air quality monitoring during demolition

Timeline and Compliance

Assessment Timeline:

  • Phase I ESA: 30-45 days
  • Phase II ESA (if required): 60-90 days
  • Wetland delineation: 45-60 days
  • Species surveys: Season-dependent (3-6 months)

Regulatory Approvals:

  • EPA coordination: 90-120 days
  • Army Corps 404 permit: 6-12 months
  • State environmental permits: 60-90 days
  • Local environmental review: 30-60 days