Some checks failed
Build and Release / Build wheels on macos-13 (pull_request) Has been cancelled
Build and Release / Build wheels on macos-14 (pull_request) Has been cancelled
Build and Release / Build wheels on ubuntu-latest (pull_request) Has been cancelled
Build and Release / Build wheels on windows-latest (pull_request) Has been cancelled
Build and Release / Build zipapp (.pyz) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (ubuntu-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.10) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.11) (pull_request) Has been cancelled
CI/CD Pipeline / test (windows-latest, 3.12) (pull_request) Has been cancelled
CI/CD Pipeline / security-scan (pull_request) Has been cancelled
CI/CD Pipeline / auto-update-check (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (macos-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Test installation methods (ubuntu-latest, 3.8) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.11) (pull_request) Has been cancelled
Build and Release / Test installation methods (windows-latest, 3.12) (pull_request) Has been cancelled
Build and Release / Publish to PyPI (pull_request) Has been cancelled
Build and Release / Create GitHub Release (pull_request) Has been cancelled
- Tested FSS-Mini-RAG with real estate development documentation - Created intelligent knowledge base for domain queries - Evaluated search effectiveness for professional workflows - Documented 2 critical issues found - Rating: 7/10 overall effectiveness 🤖 Generated with [Claude Code](https://claude.ai/code) Co-Authored-By: Claude <noreply@anthropic.com>
4.6 KiB
4.6 KiB
Environmental Impact Assessment Requirements
Mixed-Use Development Projects
Phase I Environmental Site Assessment
Required for all projects exceeding:
- 2 acres of development
- 50 residential units
- 25,000 sq ft of commercial space
Assessment Components:
- Historical land use review dating back 50 years
- Review of environmental databases (CERCLIS, RCRA, UST)
- Site reconnaissance and photographic documentation
- Interviews with knowledgeable parties
- Assessment of recognized environmental conditions (RECs)
Phase II Environmental Assessment Triggers
Required when Phase I identifies:
- Former gas stations or automotive facilities within 500 feet
- Dry cleaning operations (historical or current)
- Industrial facilities with chemical storage
- Underground storage tanks (active or abandoned)
- Soil or groundwater contamination potential
Wetland Delineation Requirements
Mandatory assessment if site contains:
- Seasonal water accumulation areas
- Hydric soils indicators
- Wetland vegetation communities
- Areas within 100 feet of water bodies
Process Requirements:
- Professional wetland scientist evaluation
- Army Corps of Engineers jurisdictional determination
- 404 permit application if impacts exceed 0.1 acres
- Mitigation banking or on-site compensation plans
Stormwater Management Compliance
Post-Construction Requirements:
- Retention of first 1.2 inches of rainfall on-site
- Peak discharge rates not to exceed pre-development conditions
- Water quality treatment for 90% of annual runoff
- Long-term maintenance agreements with approved entities
Green Infrastructure Requirements:
- Minimum 30% of stormwater managed through green infrastructure
- Permeable pavement for minimum 25% of parking areas
- Bioretention areas sized for 10-year storm events
- Tree canopy coverage of 40% within 10 years
Air Quality Impact Analysis
Required for projects with:
- More than 500 vehicle trips per day
- Parking for 200+ vehicles
- Commercial uses generating odors or emissions
Assessment Components:
- Mobile source emission calculations
- Construction dust control plans
- Indoor air quality considerations for residential units
- Compliance with National Ambient Air Quality Standards
Noise Impact Assessment
Trigger Levels:
- Projects within 1,500 feet of highways or arterial roads
- Mixed-use with late-night commercial operations
- Loading docks or mechanical equipment on-site
Standards:
- Residential areas: 55 dB daytime, 45 dB nighttime
- Commercial areas: 65 dB daytime, 55 dB nighttime
- Mitigation required if increases exceed 3 dB over ambient
Historic and Cultural Resource Review
Section 106 Review Required:
- Properties 50+ years old within 0.5 miles
- Areas of known archaeological significance
- Traditional cultural properties consultation with tribal authorities
Documentation Requirements:
- Historic structures report
- Archaeological survey (if ground disturbance >1 acre)
- Tribal consultation documentation
- State Historic Preservation Office coordination
Soil and Groundwater Assessment
Contamination Screening:
- Lead paint analysis for structures built before 1978
- Asbestos survey for buildings constructed 1940-1980
- Petroleum hydrocarbon testing near former fuel facilities
- Heavy metals analysis in urban brownfield areas
Remediation Thresholds:
- Residential soil standards apply to all residential components
- Groundwater monitoring required if contamination detected
- Vapor intrusion assessment for volatile compounds
- Institutional controls may be required for contained contamination
Wildlife and Habitat Protection
Protected Species Assessment:
- Endangered species habitat surveys during breeding seasons
- Migratory bird nesting surveys (March-August)
- Tree surveys for protected or heritage specimens
- Pollinator habitat preservation requirements
Construction Environmental Controls
Erosion and Sediment Control:
- SWPPP (Stormwater Pollution Prevention Plan) required
- Daily inspection and maintenance logs
- Stabilization within 7 days of final grade
- Temporary seeding for areas disturbed >30 days
Dust Control Measures:
- Water application during dry conditions
- Stabilized construction entrances
- Vehicle tracking prevention
- Air quality monitoring during demolition
Timeline and Compliance
Assessment Timeline:
- Phase I ESA: 30-45 days
- Phase II ESA (if required): 60-90 days
- Wetland delineation: 45-60 days
- Species surveys: Season-dependent (3-6 months)
Regulatory Approvals:
- EPA coordination: 90-120 days
- Army Corps 404 permit: 6-12 months
- State environmental permits: 60-90 days
- Local environmental review: 30-60 days